During Phase E - Opportunties and Solutions, a gap analysis can be used to compare the ____ between the as-is and the to-be architecture.
A. requirements
B. Solution Building Blocks
C. Architecture Building Blocks
D. business functions
E. standards
Answer: D
Answer: D
What is the objective of Phase F?
A. To establish the IT Governance framework that will be used to direct deployment.
B. To sort the implementation projects into priority order for implementation and migration.
C. To implement change management processes that will be used to manage the implementation projects.
D. To validate the architecture vision.
E. All of these tasks
Answer: B
Answer: B